Our Journey

From a foundation stone on Tokipur Road to a full-service hospital, eight years in the making. Every photograph below is from the original project archive.

Architect's impression of Gobindaganj General Hospital
  1. Early 2017

    The Master Plan

    Before construction began, the hospital was designed as a purpose-built facility: an artist's impression, detailed floor plans and a location map set out what would rise on Tokipur Road.

    + 2 more photos

  2. March 2017

    The Foundation Stone

    In March 2017 the foundation stone was laid on Tokipur Road. The ceremony, attended by local well-wishers, marked the official start of construction.

    + 1 more photos

    Foundation laying ceremony, 19 March 2017 (streamed from the original project archive)

  3. April 2017

    Partnership MoU

    A memorandum of understanding signed in April 2017 formalised a key partnership in support of the hospital project.

  4. August 2017

    The Boundary Wall Rises

    By August 2017 the site was enclosed. The boundary wall rose along the hospital grounds, with early site works under way.

    + 4 more photos

    Archived footage of the boundary wall construction

  5. March 2018

    Road and Site Works

    The hospital approach road was built in early 2018, connecting the site to Tokipur Road and easing access for construction and, later, patients.

  6. May 2018

    The Ward Block Begins

    Piling and groundwork for the main ward block began in May 2018 — the first vertical structure of the hospital.

    + 1 more photos

    Ward block construction, 25 May 2018

    Site progress, 28 May 2018

  7. August 2018

    The Structure Takes Shape

    Through the summer of 2018 the concrete frame of the ward block rose floor by floor.

  8. September 2018

    Ground and First Floors

    By late September 2018 the ground and first floors were clearly visible above the boundary wall.

  9. October 2018

    Autumn Progress

    By October 2018 the full structure stood above the trees, with brickwork following the concrete frame.

  10. February 2019

    Finishing Works

    In February 2019 attention turned inside: foundations were completed and finishing works progressed across the building.

    + 2 more photos

  11. 30 January 2025

    Grand Inauguration

    Gobindaganj General Hospital was formally inaugurated on 30 January 2025.

    Hospital highlights video

  12. 8 February 2025

    Doors Open to Patients

    On 8 February 2025 the hospital began serving patients — outpatient, emergency, diagnostic and inpatient care, close to home.